Previous projects

Project NameDescription of worksClientValue (in Rand)Contract DurationYear of completion
Caltex JunctionKnockdown Rebuild CanopyChevron4 061 3423 months2018
Caltex SummerfieldKnockdown RebuildChevron2 011 8123 months2018
Caltex Crown MineKnockdown RebuildCanopyChevron3 663 5773 months2018
Caltex Eldorado ParkKnockdown RebuildAstron Energy3 428 7773 months2019
Caltex LinksfieldKnockdown RebuildCanopyAstron Energy4 853 9423 months2019
Caltex ClevelandKnockdown RebuildCanopy|BuildingAstron Energy|Private5 895 2254 months2019
Grootvlei DSLKnockdown RebuildCanopyPrivate3 888 3472.5 months2020
Caltex NasumaKnockdown RebuildCanopy|BuildingAstron Energy|Private8 1557 705 months2020-2021
Randfontein Truck StopDiesel depotPrivate1 220 5356 weeks2021
Caltex GroblersdalKnockdownRebuildPrivate4 148 5508 weeks2021